AwardedAwarded 11 November 2025
904724896 T1350 Understanding root causes and preventing freight wagon wheel flats Work Package 3 – Static Brake Testing of Freight Vehicles
Rail Safety Standards Board (RSSB) · Public undertaking
In brief
Rail Safety Standards Board (RSSB) awarded research work to Engineering Support Group Limited on 11 November 2025.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
At the highest level, this work package seeks to provide missing empirical data which will support decision making and modelling to better understand how the behaviour of freight braking systems impact on the generation of wheel flats. This project will seek to characterise and document the behaviour of freight braking systems in real world settings. In combination with the other work packages, the outputs of this study will be used to inform the conclusions of the project overall and will provide useful input to other research activities on freight safety. Specifically, the outputs from this work package will support the research in characterising longitudinal compressive forces in…Read the full description
At the highest level, this work package seeks to provide missing empirical data which will support decision making and modelling to better understand how the behaviour of freight braking systems impact on the generation of wheel flats.
This project will seek to characterise and document the behaviour of freight braking systems in real world settings. In combination with the other work packages, the outputs of this study will be used to inform the conclusions of the project overall and will provide useful input to other research activities on freight safety. Specifically, the outputs from this work package will support the research in characterising longitudinal compressive forces in freight (T1352), and the investigation into the factors impacting freight braking in low adhesion (T1351).
The outputs will be achieved through a variety of static brake tests of real freight trains. The specific objectives of the project will be to:
1.Identify suitable testing parameters or categorisation to prioritise testing and agree a test regime.
2.Understand the performance of different locomotives.
3.Understand how braking behaviour varies with different vehicles, brake setups and components.
4.Understand how brake timing and brake force varies down the length of a long train.
5.Understand how different charging/overcharge procedures influence the behaviour of braking systems.
Whilst delivering these objectives will have implications on freight braking and deceleration performance. The primary objective of this work is to support research in the topic of freight safety.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=1001646902
Who won
| Winner | Value | Dates |
|---|---|---|
| Engineering Support Group Limited | £120,000 | 18 November 2025 to 10 April 2026 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Contract details notice · UK7, notice 083297-2025
About the buyer
Rail Safety Standards Board (RSSB)Last 12 months
Procurements
46Awards
22Suppliers it has used most for research
- Ove Arup & Partners Ltd2 contracts
- Andromeda Engineering Ltd1 contract
- DGauge Ltd1 contract
- Engineering Support Group Limited1 contract
- OptiConsulting Limited1 contract
Similar open tenders
All open research tenders- £350kestimated
- £100kestimated
- £80kestimated
- £260mframework ceiling
- £170kestimated