Cancelled
Broomhills Pavilion Upgrade
Repton Parish Council · Local authority
In brief
Repton Parish Council has cancelled this procurement.
The estimated value is £100,000 excluding VAT.
The contract runs for 4 months, starting 1 January 2026.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
1 Site Location Broomhills Pavilion is located adjacent to playing fields at the top of Broomhills Lane Repton DE65 6FS The building is of brick and tile, single storey construction. Services provided are three phase electricity, water and sewerage. All existing room heating arrangements are to be retained. It is envisaged that bidders will need to undertake a detailed inspection of the existing building. Details for the arrangement of site visits are given in section 5 below. 2 Scope of Supply The contract will require the completion of all works associated with the following listed requirements. 2.1 Building 2.1.1 Inspect and repair any defective areas of the roof covering. 2.1.2 Replace…Read the full description
1 Site Location
Broomhills Pavilion is located adjacent to playing fields at the top of Broomhills Lane Repton DE65 6FS
The building is of brick and tile, single storey construction. Services provided are three phase electricity, water and sewerage. All existing room heating arrangements are to be retained.
It is envisaged that bidders will need to undertake a detailed inspection of the existing building. Details for the arrangement of site visits are given in section 5 below.
2 Scope of Supply
The contract will require the completion of all works associated with the following listed requirements.
2.1 Building
2.1.1 Inspect and repair any defective areas of the roof covering.
2.1.2 Replace all gutters and downpipes.
2.1.3 Replace Insulation.
2.1.4 Install thermal expansion joint in south wall and make good cracked brickwork.
2.1.5 Provide Wheel Chair Access to Main Door
2.1.6 Provide simple canopy over main entrance from entrance doors to the front of the building but not extending beyond building.
2.1.7 Entrance external light and switch with delay switch off
2.2 Plant & Equipment Room
2.2.1 Removal of existing plant & equipment providing hot and cold water to showers, washbasins and kitchen.
2.2.2 Provide a suitable energy efficient, electrical water heating arrangement to supply the refurbished building.
2.2.3 Provide lockable enclosure covering electric supply and main switches.
2.2.4 Modify old plant room to provide a change facility for Match Official with washbasin, toilet etc.
2.2.5 Install tiling where appropriate and decorate throughout.
2.3 Main function room
(Existing electrical heating units to be retained)
2.3.1 Repair floorcovering as required.
2.3.2 Create serving counter to adjoining kitchen area with storage units under the counter.
2.3.3 Make good all surfaces.
2.3.4 Replace skirting and architraves where necessary.
2.3.5 Replace frosted Glass in double doors upper sections with suitable clear glass
2.3.6 Provide window in west wall (2.5m x 1.2m) double glazed glass, lockable.
2.3.7 Decorate throughout.
2.4 Kitchen
2.4.1 Replace all units and provide double sink, large frig and dishwasher only. (No cooking appliances required)
2.4.2 Units to include one tall cupboard suitable for cleaning apparatus and equipment.
2.4.2 Install tiling where appropriate and decorate throughout.
2.5 Reception area
2.5.1 Remove existing cupboards.
2.5.2 Make good all surfaces.
2.5.3 Replace internal doors with safety glass and compliant fire-resistant doors as required.
2.5.4 Provide tall lockable storage cupboard for RPC use, to south of main doors. To include a double electrical power socket. (CCTV recorder position)
2.5.5 Decorate throughout.
2.6 Toilets
2.6.1 Remove existing toilets and replace with two accessible toilets in each block, to include required ventilation. (FA Guidance)
2.6.2 Tile as required and decorate throughout.
2.7 Shower & Changing Rooms
2.7.1 Provide proposals for a modern shower installation to replace existing arrangements.
2.7.2 Refurbish existing tiled floors.
2.7.3 Install suitable ventilation.
2.7.4 Install / repair tiling where appropriate.
2.7.5 Make good ceilings suitable for shower / changing room environment.
2.7.6 Provide small key lockable box / safe for each changing room.
2.7.7 Decorate throughout.
2.8 Electrical
(note current emergency lighting system and safety equipment is considered satisfactory)
2.8.1 Ensure existing electrical installation and wiring meets current building standards and IEE regulations, replace and rewire as necessary.
2.8.2 Beyond the requirements listed above, ensure there are double 13 Amp sockets - two in east side wall of the main function room, two on main function room wall next to the entrance, one on west wall of main function room (one suitable for use on the new counter, two on each long wall of the kitchen,
2.8.3 Replace all lights with LED lights as required.
2.8.4 Provide ducting / cabling / terminal boxes for potential CCTV cameras and LED lights at the four corners of the building to the lockable cupboard in the reception area.
Who won
| Winner | Value | Dates |
|---|
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Tender notice · UK4, notice 065169-2025
- Procurement termination notice · UK12, notice 065172-2025
About the buyer
Repton Parish CouncilLast 12 months
Procurements
1Awards
0Similar open tenders
All open building maintenance tenders- £400kestimated
- £8mframework ceiling
- £590kestimated
- £4.5mframework ceiling
- £8bnframework ceiling
From notice 065169-2025 on Find a Tender, first published 14 October 2025, last updated 14 October 2025. We last checked for changes on 27 September 2026.