AwardedAwarded 24 February 2026

Fire Safety Consultancy - Byker

Karbon Homes · Housing

In brief

Karbon Homes awarded this contract to Part B Group Ltd on 24 February 2026.

Built from the notice's own fields. Always check the official notice before you bid.

What the notice says

GAP analysis and a Retrospective Fire Strategy report that presents the key fire safety aspects for each of the 3no BSR Registrations listed below: BYKER WALL (DUNN TERRACE) - BSR Registration - HRB12665Y4Q2 • BYKER WALL (SHIPLEY STREET) - BSR Registration - HRB12659C5R6 • BYKER WALL (GRACE LEE) - BSR Registration - HRB12215H3Y7 • Pilot Scheme - Byker Crescent • Low-Rise Buildings

Who won

WinnerValueDates
Part B Group Ltd (SME)
1 bid received
£354,000

Values as the award notice gives them, excluding VAT where stated.

Timeline

  1. Contract award notice · notice 016467-2026

About the buyer

From notice 016467-2026 on Find a Tender, first published 24 February 2026. We last checked for changes on 28 September 2026.