AwardedAwarded 30 April 2026
Herefordshire Western Bypass Phase 1
Herefordshire Council · Local authority
In brief
Herefordshire Council awarded construction and highways work to John Graham Construction Limited on 30 April 2026.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
The project is for the Design and Build of the first phase of the Hereford Western Bypass (HWB1) . The route of the proposed HWB1 is approximately 3.5 km in length and is located on the outskirts to the southwest of Hereford.
Who won
| Winner | Value | Dates |
|---|---|---|
| John Graham Construction Limited 3 bids received | £1,859,960 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Contract award notice · notice 045070-2026
About the buyer
Herefordshire CouncilLast 12 months
Procurements
107Awards
73Suppliers it has used most for construction
- S C Joseph Ltd14 contracts
- CF Roberts (Electrical Contractors) Limited3 contracts
- Cambrensis Civil Engineering Limited3 contracts
- Owen Pell Limited3 contracts
- SC Joseph3 contracts
Similar open tenders
All open construction tenders- £250kestimated
- £2.2mestimated
- £36.6mestimated
- £110kestimated
- £160kestimated
From notice 045070-2026 on Find a Tender, first published 15 May 2026. We last checked for changes on 28 September 2026.