AwardedAwarded 26 October 2026
Location Strategy: Main Works
Bank of England · Central government
In brief
Bank of England awarded construction work to Sir Robert McAlpine Ltd (8) on 26 October 2026.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
The Bank is seeking a highly experienced, appropriately resourced and capable Main Contractor to deliver the Main Works associated with the consolidation and refurbishment of its Threadneedle Street estate, as part of the Bank's Location Strategy Project. The Project represents a significant investment in the long-term stewardship of the Bank's estate and involves the delivery of a complex construction programme. The Bank expects the appointed Main Contractor to demonstrate a high standard of competence in planning, coordination and execution, together with a disciplined approach to safety, quality, programme and cost control The Main Works and associated services included in the scope…Read the full description
The Bank is seeking a highly experienced, appropriately resourced and capable Main Contractor to deliver the Main Works associated with the consolidation and refurbishment of its Threadneedle Street estate, as part of the Bank's Location Strategy Project.
The Project represents a significant investment in the long-term stewardship of the Bank's estate and involves the delivery of a complex construction programme. The Bank expects the appointed Main Contractor to demonstrate a high standard of competence in
planning, coordination and execution, together with a disciplined approach to safety, quality, programme and cost control
The Main Works and associated services included in the scope of this procurement include, but is not limited to:
• General pre-construction services;
• Section-specific pre-construction services;
• General and Section-specific preliminaries;
• Works to be delivered in Sections with Sections that cover a wide range of scope, including, but not limited to:
o Preparatory Works
o Replacement of core infrastructure
o Ground Floor
o Auditorium
o Workplace Floors
o Basement Works
The exact scope of each Section will be developed during the pre-construction stage. An indicative description of the Sections is set out in the Statement of Requirements. The Bank reserves the right to refine, expand, reduce, or omit the scope, content, and timing of any Section prior to its instruction. No Section will proceed unless and until the Bank issues a formal notice to proceed for that Section.
The Bank intends to (and reserves the right to) directly award additional or repeat works that are similar to the works supplied under the contract which is the subject matter of this Tender Notice, in accordance with Schedule 5, paragraph 8 of PA 2023.
Who won
| Winner | Value | Dates |
|---|---|---|
| Sir Robert McAlpine Ltd (8) 4 bids received | £133,000,000 | Awarded 26 October 2026 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Contract award notice · UK6, notice 101071-2026
About the buyer
Bank of EnglandLast 12 months
Procurements
147Awards
108Suppliers it has used most for construction
- E & B Group Limited2 contracts
- Volmech Limited2 contracts
- Flooring Trade Ltd1 contract
- Impulse Engineering Limited1 contract
- Navarre London1 contract
Similar open tenders
All open construction tenders- £235kestimated
- £450mframework ceiling
- £280mestimated
- £600kframework ceiling
- £225kestimated
From notice 101071-2026 on Find a Tender, first published 26 October 2026. We last checked for changes on 26 October 2026.