AwardedAwarded 30 January 2026

New Build Housing Framework Agreement

The City of Edinburgh Council · Local authority

In brief

The City of Edinburgh Council awarded construction work to Campion Homes Ltd, A.s. Homes (Scotland) Limited and Fleming Buildings Ltd and 5 others on 30 January 2026.

It is split into 3 lots, so a supplier can bid for part of the work.

Built from the notice's own fields. Always check the official notice before you bid.

What the notice says

The City of Edinburgh Council (CEC) wishes to appoint contractors to a Framework Agreement to deliver elements of the Council’s House Building Programme. The Council and RSL partners have an ambition to construct approximately 25,000 new affordable homes. There are also opportunities for other organisations to utilise the Framework Agreement. In order to realise these goals, the Council requires an efficient route to market for the design and construction of affordable, new build housing across the city. Typically, the Council’s delivery model for new build housing is via the following methods; (a) On land currently owned by the Council or acquired for this purpose (b) By purchasing parts of developments being built privately. (c) On Council owned land where, due to complexity, it enters into development partnerships (generally for mixed tenure and mixed-use developments) The New Build Housing Framework Agreement that this Framework Agreement relates to will primarily, but not exclusively, manage projects delivered via option (a) as above. However, successful organisations should be amenable and able to facilitate the procuring of options (b) and (c) where required. This Framework Agreement is open to all organisations named in this notice.

Lots

LotTradeValue
Lot 1-1 - Residential Construction - 1 to 30 Homes
What this lot covers

The City of Edinburgh Council (CEC) wishes to appoint contractors to a Framework Agreement to deliver elements of the Council’s Housebuilding Programme. The Council and RSL partners have an ambition to construct approximately 25,000 new affordable homes. There are also opportunities for other organisations to utilise the Framework Agreement. In order to realise these goals, the Council requires an efficient route to market for the design and construction of affordable, new build housing across the city. Typically, the Council’s delivery model for new build housing is via the following methods; (a) On land currently owned by the Council or acquired for this purpose (b) By purchasing parts of developments being built privately. (c) On Council owned land where, due to complexity, it enters into development partnerships (generally for mixed tenure and mixed-use developments) The New Build Housing Framework Agreement that this Framework Agreement relates to will primarily, but not exclusively, manage projects delivered via option (a) as above. However, successful organisations should be amenable and able to facilitate the procuring of options (b) and (c) where required. There is a strong desire to innovate in the design and construction of the new homes and to deliver sustainable communities through place-making. All homes will be constructed, as a minimum, to net zero carbon and the Council is seeking to innovate beyond this standard where real benefit can be provided for tenants. Through the construction of new housing, the Council is seeking to support the Council’s Business Plan and Core Principles as well as promote and encourage the following outcomes; - Compliance with the Council’s Design Guide - Quality Management and Assurance - Accelerating delivery and promoting innovation throughout design and construction - Cost Compliance/Achieving Best Value - Experience of working with different Forms of Contract and Procurement Approaches - Collaboration with different stakeholders and partners - Working with SME’s and Local Supply Chains including compliance with prompt payment terms - Operating in a sustainable manner and achieving sustainable outcomes - The delivery of community benefits aligned to the needs of the local area and Council tenants - Compliance with Fair Working Practices/Initiatives - Impact positively on the Housing Emergency, which was declared in 2023. The Framework Agreement comprises of 3 Lots - Lot 1.1 sites ranging from 1 home to 30 homes, Lot 1.2 sites ranging from 31 to 100 homes and Lot 1.3 sites with 100+ homes. This Lot shall cover both Build Only (where the contractor fulfils a design provided by the Council) and Design and Build (where the contractor has full design responsibility following the Council’s supplied brief) requirements. It is anticipated that the majority of projects utilising the Framework Agreement will focus on building affordable homes. However, mixed tenure may also be utilised in certain circumstances as well as other residential schemes, including but not limited to, care homes, nurseries, supported living accommodation and temporary accommodation. Design team novation will need to be accepted and managed appropriately by successful organisations where applicable.

Construction—
Lot 1.2 - Residential Construction - 31 to 100 Homes
What this lot covers

The City of Edinburgh Council (CEC) wishes to appoint contractors to a Framework Agreement to deliver elements of the Council’s Housebuilding Programme. The Council and RSL partners have an ambition to construct approximately 25,000 new affordable homes. There are also opportunities for other organisations to utilise the Framework Agreement. In order to realise these goals, the Council requires an efficient route to market for the design and construction of affordable, new build housing across the city. Typically, the Council’s delivery model for new build housing is via the following methods; (a) On land currently owned by the Council or acquired for this purpose (b) By purchasing parts of developments being built privately. (c) On Council owned land where, due to complexity, it enters into development partnerships (generally for mixed tenure and mixed-use developments) The New Build Housing Framework Agreement that this Framework Agreement relates to will primarily, but not exclusively, manage projects delivered via option (a) as above. However, successful organisations should be amenable and able to facilitate the procuring of options (b) and (c) where required. There is a strong desire to innovate in the design and construction of the new homes and to deliver sustainable communities through place-making. All homes will be constructed, as a minimum, to net zero carbon and the Council is seeking to innovate beyond this standard where real benefit can be provided for tenants. Through the construction of new housing, the Council is seeking to support the Council’s Business Plan and Core Principles as well as promote and encourage the following outcomes; - Compliance with the Council’s Design Guide - Quality Management and Assurance - Accelerating delivery and promoting innovation throughout design and construction - Cost Compliance/Achieving Best Value - Experience of working with different Forms of Contract and Procurement Approaches - Collaboration with different stakeholders and partners - Working with SME’s and Local Supply Chains including compliance with prompt payment terms - Operating in a sustainable manner and achieving sustainable outcomes - The delivery of community benefits aligned to the needs of the local area and Council tenants - Compliance with Fair Working Practices/Initiatives - Impact positively on the Housing Emergency, which was declared in 2023. Lot 1.2 will comprise of sites ranging from 31 home to 100 homes. This Lot shall cover both Build Only (where the contractor fulfils a design provided by the Council) and Design and Build (where the contractor has full design responsibility following the Council’s supplied brief) requirements. It is anticipated that the majority of projects utilising the Framework Agreement will focus on building affordable homes. However, mixed tenure may also be utilised in certain circumstances as well as other residential schemes, including but not limited to, care homes, nurseries, supported living accommodation and temporary accommodation. Design team novation will need to be accepted and managed appropriately by successful organisations where applicable.

Construction—
Lot 1.3 - Residential Construction - 100+ Homes
What this lot covers

The City of Edinburgh Council (CEC) wishes to appoint contractors to a Framework Agreement to deliver elements of the Council’s Housebuilding Programme. The Council and RSL partners have an ambition to construct approximately 25,000 new affordable homes. There are also opportunities for other organisations to utilise the Framework Agreement. In order to realise these goals, the Council requires an efficient route to market for the design and construction of affordable, new build housing across the city. Typically, the Council’s delivery model for new build housing is via the following methods; (a) On land currently owned by the Council or acquired for this purpose (b) By purchasing parts of developments being built privately. (c) On Council owned land where, due to complexity, it enters into development partnerships (generally for mixed tenure and mixed-use developments) The New Build Housing Framework Agreement that this Framework Agreement relates to will primarily, but not exclusively, manage projects delivered via option (a) as above. However, successful organisations should be amenable and able to facilitate the procuring of options (b) and (c) where required. There is a strong desire to innovate in the design and construction of the new homes and to deliver sustainable communities through place-making. All homes will be constructed, as a minimum, to net zero carbon and the Council is seeking to innovate beyond this standard where real benefit can be provided for tenants. Through the construction of new housing, the Council is seeking to support the Council’s Business Plan and Core Principles as well as promote and encourage the following outcomes; - Compliance with the Council’s Design Guide - Quality Management and Assurance - Accelerating delivery and promoting innovation throughout design and construction - Cost Compliance/Achieving Best Value - Experience of working with different Forms of Contract and Procurement Approaches - Collaboration with different stakeholders and partners - Working with SME’s and Local Supply Chains including compliance with prompt payment terms - Operating in a sustainable manner and achieving sustainable outcomes - The delivery of community benefits aligned to the needs of the local area and Council tenants - Compliance with Fair Working Practices/Initiatives - Impact positively on the Housing Emergency, which was declared in 2023. Lot 1.3 will comprise of all sites over 100 homes. This Lot shall cover both Build Only (where the contractor fulfils a design provided by the Council) and Design and Build (where the contractor has full design responsibility following the Council’s supplied brief) requirements. It is anticipated that the majority of projects utilising the Framework Agreement will focus on building affordable homes. However, mixed tenure may also be utilised in certain circumstances as well as other residential schemes, including but not limited to, care homes, nurseries, supported living accommodation and temporary accommodation. Design team novation will need to be accepted and managed appropriately by successful organisations where applicable.

Construction—

Who won

WinnerLotValueDates
Campion Homes Ltd
A.s. Homes (Scotland) Limited (SME)
Fleming Buildings Ltd (SME)
Lot 1-1 - Residential Construction - 1 to 30 Homes£15,000,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Robertson Group Ltd.
Lot 1.2 - Residential Construction - 31 to 100 Homes£167,500,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Ogilvie Construction Limited (SME)
Lot 1.3 - Residential Construction - 100+ Homes£167,500,000
Campion Homes Ltd
A.s. Homes (Scotland) Limited (SME)
Fleming Buildings Ltd (SME)
Lot 1-1 - Residential Construction - 1 to 30 Homes£15,000,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Robertson Group Ltd.
Lot 1.2 - Residential Construction - 31 to 100 Homes£167,500,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Ogilvie Construction Limited (SME)
Lot 1.3 - Residential Construction - 100+ Homes£167,500,000
Campion Homes Ltd
A.s. Homes (Scotland) Limited (SME)
Fleming Buildings Ltd (SME)
Lot 1-1 - Residential Construction - 1 to 30 Homes£15,000,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Robertson Group Ltd.
Lot 1.2 - Residential Construction - 31 to 100 Homes£167,500,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Ogilvie Construction Limited (SME)
Lot 1.3 - Residential Construction - 100+ Homes£167,500,000
Campion Homes Ltd
A.s. Homes (Scotland) Limited (SME)
Fleming Buildings Ltd (SME)
Lot 1-1 - Residential Construction - 1 to 30 Homes£15,000,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Robertson Group Ltd.
Lot 1.2 - Residential Construction - 31 to 100 Homes£167,500,000
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Ogilvie Construction Limited (SME)
Lot 1.3 - Residential Construction - 100+ Homes£167,500,000
Campion Homes Ltd
A.s. Homes (Scotland) Limited (SME)
Fleming Buildings Ltd (SME)
CCG (Scotland) Ltd
Cruden Investments Limited
McTaggart Construction Ltd
Robertson Group Ltd.
Ogilvie Construction Limited (SME)
Lot 1-1 - Residential Construction - 1 to 30 Homes£350,000,000

Values as the award notice gives them, excluding VAT where stated.

Timeline

  1. Contract award notice · notice 017397-2026
  2. Contract award notice · notice 017401-2026
  3. Contract award notice · notice 017406-2026
  4. Contract award notice · notice 017867-2026
  5. Contract award notice (update) · notice 064842-2026

About the buyer

Procurements

55

Awards

28

Suppliers it has used most for construction

Similar open tenders

All open construction tenders
  1. Asbestos Management Framework

    Home GroupNorth East, North West, Yorkshire and the Humber, East Midlands, West Midlands, East of England, London, South East, South West, ScotlandArchitecture and engineering, Construction

    Closing soon11 hours leftExpress interest8 lotsSuitable for SMEsFramework

    £5mframework ceiling
  2. Asbestos Management Framework

    Home GroupNorth East, North West, Yorkshire and the Humber, East Midlands, West Midlands, East of England, London, South East, South West, ScotlandArchitecture and engineering, Construction

    Closing soon11 hours left8 lotsSuitable for SMEsFramework

    £5mframework ceiling
  3. Molendinar+Reidvale HAs Landscape Maintenance Framework 2027

    Molendinar Park Housing Association LimitedScotlandGrounds maintenance and landscaping, Construction

    Closing soon3 days leftFramework

    Value not stated
  4. Home Group Responsive, Voids and DAPA Works – Dumfries and Galloway Scotland

    Home Group ScotlandScotlandConstruction

    Closing soon3 days left

    £2mestimated
  5. Water Hygiene Services

    Caledonian Sleeper LimitedScotlandHealthcare services, Construction

    Closing soon3 days left

    £680kestimated

From notice 017397-2026 on Find a Tender, first published 26 February 2026, last updated 9 July 2026. We last checked for changes on 28 September 2026.