AwardedAwarded 30 March 2026
Power supply for server room move
Centre for Process Innovation Limited · Public undertaking
In brief
Centre for Process Innovation Limited awarded construction and electrical work to JBA Engineering ltd on 30 March 2026.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
To facilitate CPI server room to be moved locations, CPI requires first ranked supplier on it's Electrical Works Framework to provide and install a 63A single-phase dual-feed changeover switch, fed via T-block tap-in box and H-tap-in box connections. The changeover switch will supply a single-phase distribution board serving 2 × 16A commando socket outlets and 1 × 20A air-conditioning supply.
Who won
| Winner | Value | Dates |
|---|---|---|
| JBA Engineering ltd (SME) | — | 30 March 2026 to 29 March 2027 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Contract details notice · UK7, notice 045023-2026
About the buyer
Centre for Process Innovation LimitedLast 12 months
Procurements
100Awards
63Suppliers it has used most for construction
- JBA Engineering ltd2 contracts
- ACEDA Limited1 contract
- Ambient Air Conditioning UK Ltd1 contract
- Anelec Group Limited1 contract
- G&B Civil Engineering Ltd1 contract
Similar open tenders
All open construction tenders- £5mframework ceiling
- £5mframework ceiling
- £81kestimated
- £1mestimated
- £163mframework ceiling
From notice 045023-2026 on Find a Tender, first published 15 May 2026. We last checked for changes on 28 September 2026.