Re-Roofs Hull City Council 2026 - 2028
Kingstown Works Limited · Local or regional public body
In brief
Kingstown Works Limited awarded construction and building maintenance work to Snug Services Group Limited, M & J Group (Construction & Roofing) Ltd and Specialised Group Ltd and 14 others on 17 September 2026.
It is a framework worth up to £2,700,000 excluding VAT: the most the buyer expects to spend across all suppliers, not one contract.
The contract runs for 18 months, starting 1 November 2026.
It is split into 5 lots, so a supplier can bid for part of the work.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
Lots
| Lot | Trade | Value |
|---|---|---|
| Pitch Roofing 1 November 2026 to 30 April 2028 What this lot coversSub-contractors will be expected to complete a minimum of 2 properties per week. There are an expected 245 properties in total that will require pitch roofs. Pricing must cover all items listed on Lot 1 as listed within Document 3 - Price Schedule, failure to provide a fully completed price schedule for this lot will result in your organisation being removed from the tender at the selection stage of the process and you will not progress to the award stage of the contract. Please see section 3 - Selection Criteria for further information. Please ensure that you refer to and complete the individual tabs for each property (the individual tabs are located after the Lot tabs and start off with the listing for 2 Jipdane)- prices must be put in the columns highlighted in yellow. , When the prices are entered in the yellow columns individual property spreadsheets the price schedule will automatically populate the price per property overview tab with the relevant price information in the column highlighted in Yello (Lot 1 - Pitch Roof - Overview) All pricing must be returned on the Price Schedule provided; quotes will not be accepted. The usage figures quoted either in this document or Document 3 - Price Schedule are estimated figures only and KWL can offer no guarantee of spend, volume or frequency of orders made to any sub-contractor. Sub-contractors will be monitored on the following KPI's. • 90% of orders completed to the agreed programme of works. • 90% of tenants who were satisfied with the planned works, when asked. • 90% of planned works where the quality of work was to the required standard when inspected by HIS Sub-contractors should refer to the relevant documents contained within the tender bundle. Complete tender documents can be obtained by e-mailing eu.tendering@kwl.co.uk | Construction, Building maintenance and repairs | £2,000,000 |
| Flat Roofs 1 November 2026 to 30 April 2028 What this lot coversSub-contractors will be expected to complete a minimum of 1 property per week. There are an expected 27 properties in total that will require Flat Roofing Pricing must cover all items listed on Lot 2 as shown within Document 3 - Price Schedule, failure to provide a fully completed price schedule for this lot will result in your organisation being removed from the tender at the selection stage of the process and you will not progress to the award stage of the contract. Please see section 3 - Selection Criteria for further information All pricing must be returned on the Price Schedule provided; quotes will not be accepted. The usage figures quoted either in this document or Document 3 - Price Schedule are estimated figures only and KWL can offer no guarantee of spend, volume or frequency of orders made to any sub-contractor. Sub-contractors will be monitored on the following KPI's. • 90% of orders completed to the agreed programme of works. • 90% of tenants who were satisfied with the planned works, when asked. • 90% of planned works where the quality of work was to the required standard when inspected by HIS Sub-contractors should refer to the relevant information contained within the tender bundle Complete tender documents can be obtained by e-mailing eu.tendering@kwl.co.uk | Construction, Building maintenance and repairs | £40,000 |
| Building - Shed Refurbishment 1 November 2026 to 30 April 2028 What this lot coversSub-contractors will be expected to complete a minimum of 1 per week. Pricing must cover all items listed on Lot 3 as shown within Document 3 - Price Schedule, failure to provide a fully completed price schedule for this lot will result in your organisation being removed from the tender at the selection stage of the process and you will not progress to the award stage of the contract. Please see section 3 - Selection Criteria for further information All pricing must be returned on the Price Schedule provided; quotes will not be accepted. The usage figures quoted either in this document or Document 3 - Price Schedule are estimated figures only and KWL can offer no guarantee of spend, volume or frequency of orders made to any sub-contractor. Sub-contractors will be monitored on the following KPI's. • 90% of orders completed to the agreed programme of works. • 90% of tenants who were satisfied with the planned works, when asked. • 90% of planned works where the quality of work was to the required standard when inspected by HIS Sub-contractors should refer to the information contained within the complete Suite of Tender Documents Complete tender documents can be obtained by e-mailing eu.tendering@kwl.co.uk | Construction | £90,000 |
| Satellite and Aerial Works 1 November 2026 to 30 April 2028 What this lot coversSub-contractors will be expected to complete a minimum of 3 TV aerial locations per week. Pricing must cover all items listed on Lot 4 as shown within Document 3 - Price Schedule, failure to provide a fully completed price schedule for this lot will result in your organisation being removed from the tender at the selection stage of the process and you will not progress to the award stage of the contract. Please see section 3 - Selection Criteria for further information All pricing must be returned on the Price Schedule provided; quotes will not be accepted. The usage figures quoted either in this document or Document 3 - Price Schedule are estimated figures only and KWL can offer no guarantee of spend, volume or frequency of orders made to any sub-contractor. Sub-contractors will be monitored on the following KPI's. • 90% of orders completed to the agreed programme of works. • 90% of tenants who were satisfied with the planned works, when asked. • 90% of planned works where the quality of work was to the required standard when inspected by HIS Sub-contractors should refer to the complete suite of information contained within the tender bundle. Complete tender documents can be obtained by e-mailing eu.tendering@kwl.co.uk | Construction | £90,000 |
| Scaffolding 1 November 2026 to 30 April 2028 What this lot coversSub-contractors must ensure they have the capacity to erect scaffolds as per the programme of works and then dismantle within 5 working days of receipt of off hire notice. Contractors must seek and receive approval from the KWL site supervisor/charge hand prior to dismantling a scaffold to ensure all works complete. All Scaffold Contractors are required to be National Access and Scaffolding Confederation (NASC) Accredited, Sub-contractors that fail to meet this requirement should they submit a bid for Lot 5 will be removed from the tender process at the Selection Stage and will not progress to the award stage of this tender. Pricing must cover all items listed on Lot 5 as Shown within Document 3 - Price Schedule, failure to provide a fully completed price schedule for this lot will result in your organisation being removed from the tender at the selection stage of the process and you will not progress to the award stage of the contract. Please see section 3 - Selection Criteria for further information All pricing must be returned on the Price Schedule provided; quotes will not be accepted. The usage figures quoted either in this document or Document 3 - Price Schedule are estimated figures only and KWL can offer no guarantee of spend, volume or frequency of orders made to any sub-contractor. Sub-contractors will be monitored on the following KPI's. • 90% of orders completed to the agreed programme of works. • 90% of tenants who were satisfied with the planned works, when asked. • 90% of planned works where the quality of work was to the required standard when inspected by HIS Sub-contractors should refer to the complete suite of documents contained within the tender bundle. Complete tender documents can be obtained by e-mailing eu.tendering@kwl.co.uk | — | £500,000 |
Who won
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Tender notice · UK4, notice 062795-2026
- Tender notice · UK4, notice 073088-2026
- Contract award notice · UK6, notice 088320-2026
About the buyer
Procurements
6Awards
6Suppliers it has used most for construction
- CMM Contractors Limited2 contracts
- Tilson Scaffolding Limited2 contracts
- Wyke System Engineers2 contracts
- Alternative Windows (Leeds) Limited1 contract
- Amazon Window Systems Ltd1 contract
Similar open tenders
All open construction tenders- £1.3mestimated
- £5mframework ceiling
- £5mframework ceiling
- £1mestimated
- £60kestimated
From notice 062795-2026 on Find a Tender, first published 3 July 2026, last updated 17 September 2026. We last checked for changes on 28 September 2026.