AwardedAwarded 5 June 2026

Extending High Speed Broadband Framework Agreement

Llywodraeth Cymru / Welsh Government · Central government

In brief

Llywodraeth Cymru / Welsh Government awarded this contract to BT plc, Airband Community Internet Ltd and Fibrus Ltd and 1 others on 5 June 2026.

It is a framework worth up to £70,000,000 excluding VAT: the most the buyer expects to spend across all suppliers, not one contract.

The contract runs for 8 years, starting 1 February 2026.

It is split into 2 lots, so a supplier can bid for part of the work.

The buyer says it is suitable for small and medium-sized businesses.

Built from the notice's own fields. Always check the official notice before you bid.

What the notice says

The Welsh Government has undertaken a procurement to establish a framework (the “Framework”) to deliver the Extending High Speed Broadband project (the "Project"). Once the Framework is established, the Authority intends to award a series of call-off contracts (following individual competitive selection processes), that will provide grant funding to telecoms suppliers to cover the "gap" in costs that are required to deliver superfast connections to communities / premises in Wales that would not otherwise be served by commercial operators under normal market conditions, due to the high infrastructure cost of building connections to those "hard to reach" communities / premises. Grants made…Read the full description
The Welsh Government has undertaken a procurement to establish a framework (the “Framework”) to deliver the Extending High Speed Broadband project (the "Project"). Once the Framework is established, the Authority intends to award a series of call-off contracts (following individual competitive selection processes), that will provide grant funding to telecoms suppliers to cover the "gap" in costs that are required to deliver superfast connections to communities / premises in Wales that would not otherwise be served by commercial operators under normal market conditions, due to the high infrastructure cost of building connections to those "hard to reach" communities / premises. Grants made under the call-off contracts are out of scope for the purposes of VAT. Coverage The Authority’s 2022 open market review identified that around 84,000 premises within Wales did not have access to superfast download speeds (at least 30Mbps) exacerbating the digital divide. Ofcom has previously stated that a subset of these (around 10,000 premises) do not yet have access to at least 10Mbps. Despite the efforts of the telecommunications industry and public sector interventions, there are still premises in Wales that do not have access to at least superfast broadband speeds. The Authority has therefore developed the EHSB project to address this gap and provide fast and reliable broadband to those premises. Whilst the Authority is confident that the number of premises without superfast download speeds has drastically reduced since the 2022 open market review (as the scope of commercial and other public sector deployments, including Project Gigabit, have become clearer), the Authority anticipates that the number of premises that are currently in scope of the Framework is in the region of 29,000 premises. The current, indicative list of eligible premises that are anticipated to be in scope for the Framework will be subject to refinement/update during the duration of the Framework (for example, to reflect any premises which may be addressed by other interventions). The premises that are in-scope for each call-off contract will be confirmed in the relevant request for proposals issued under the Framework. Additional Information The Framework will have two lots. The first lot (Lot 1) will be for projects that require the installation of broadband network infrastructure to 1,000 premises and over. The second lot (Lot 2) will be for projects that require the installation of broadband network infrastructure to under 1,000 premises. Suppliers were permitted to apply for either or both lots. The estimated total value set out in this notice is in respect of all call-off contracts that may be awarded under the Framework. It is an estimate only and is in no way guaranteed or final. The associated tender documents for this opportunity contain more specific information. The dates and total duration for any call-off contracts referred to in this notice or the associated procurement documents are also estimates and for illustrative purposes only.

Lots

LotTradeValue
Installation of broadband network infrastructure to 1,000 premises and over
1 February 2026 to 30 January 2034
What this lot covers

Lot 1 will be for projects that require the installation of broadband network infrastructure to 1,000 premises and over

—£60,000,000
Installation of broadband network infrastructure to under 1,000 premises
1 February 2026 to 30 January 2034
What this lot covers

Lot 2 – will be for projects that require the installation of broadband network infrastructure to under 1,000 premises.

—£10,000,000

Who won

WinnerLotValueDates
BT plc
Airband Community Internet Ltd (SME)
Fibrus Ltd (SME)
6 bids received
Installation of broadband network infrastructure to 1,000 premises and over£60,000,000
Awarded 27 March 2026
5 June 2026 to 5 June 2028
Wifinity Limited (SME)
Airband Community Internet Ltd (SME)
Fibrus Ltd (SME)
7 bids received
Installation of broadband network infrastructure to under 1,000 premises£10,000,000
Awarded 27 March 2026
5 June 2026 to 5 June 2028

Values as the award notice gives them, excluding VAT where stated.

Timeline

  1. Tender notice · UK4, notice 063081-2025
  2. Contract award notice · UK6, notice 028712-2026
  3. Contract details notice · UK7, notice 055358-2026
  4. Contract change notice · UK10, notice 079564-2026

About the buyer

Procurements

195

Awards

123

Suppliers it has used most

From notice 063081-2025 on Find a Tender, first published 8 October 2025, last updated 20 August 2026. We last checked for changes on 28 September 2026.