Housing, Regeneration and Demolition (H3) Framework
LHC Procurement Group for the Welsh Procurement Alliance (WPA) · Public undertaking
In brief
LHC Procurement Group for the Welsh Procurement Alliance (WPA) was looking for suppliers for construction and building maintenance work. Bidding has closed and no award has been published yet.
It is a framework worth up to £1,000,000,000 excluding VAT: the most the buyer expects to spend across all suppliers, not one contract.
The contract runs for 4 years, up to 5 years with extensions, starting 26 October 2026.
It is split into 12 lots, so a supplier can bid for part of the work.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
Lots
| Lot | Trade | Value |
|---|---|---|
| New Build Traditional Housing - 1 - 10 Units 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build residential (1 - 10 Units) developments across the UK, including houses, apartments, and mixed-use schemes, as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. Appointed companies will be required to act as Principal Contractor and undertake associated design responsibilities, delivering projects in compliance with all relevant regional regulations, funding requirements and standards, including those relating to building safety, energy performance, and net zero carbon objectives. Solutions may incorporate both traditional construction and Modern Methods of Construction (MMC), where appropriate to project requirements. | Construction | £100,000,000 |
| New Build Traditional Housing - 11 to 25 Units 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build residential developments (11 to 25 units) across the UK, including houses, apartments, and mixed-use schemes, as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. Appointed companies will be required to act as Principal Contractor and undertake associated design responsibilities, delivering projects in compliance with all relevant regional regulations, funding requirements and standards, including those relating to building safety, energy performance, and net zero carbon objectives. Solutions may incorporate both traditional construction and Modern Methods of Construction (MMC), where appropriate to project requirements. | Construction | £100,000,000 |
| New Build Traditional Housing - 26 to 50 Units 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build residential developments (26 to 50 Units) across the UK, including houses, apartments, and mixed-use schemes, as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. Appointed companies will be required to act as Principal Contractor and undertake associated design responsibilities, delivering projects in compliance with all relevant regional regulations, funding requirements and standards, including those relating to building safety, energy performance, and net zero carbon objectives. Solutions may incorporate both traditional construction and Modern Methods of Construction (MMC), where appropriate to project requirements. | Construction | £100,000,000 |
| New Build Traditional Housing - Over 50 Units 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build residential developments (Over 50 Units) across the UK, including houses, apartments, and mixed-use schemes, as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. Appointed companies will be required to act as Principal Contractor and undertake associated design responsibilities, delivering projects in compliance with all relevant regional regulations, funding requirements and standards, including those relating to building safety, energy performance, and net zero carbon objectives. Solutions may incorporate both traditional construction and Modern Methods of Construction (MMC), where appropriate to project requirements. | Construction | £100,000,000 |
| New Build Traditional Housing - Housing above 18m in height 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build residential developments (Housing above 18m in height) across the UK, including houses, apartments, and mixed-use schemes, as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. Appointed companies will be required to act as Principal Contractor and undertake associated design responsibilities, delivering projects in compliance with all relevant regional regulations, funding requirements and standards, including those relating to building safety, energy performance, and net zero carbon objectives. Solutions may incorporate both traditional construction and Modern Methods of Construction (MMC), where appropriate to project requirements. | Construction | £100,000,000 |
| Retrofit & Estate Regeneration - 0 to 2m value band 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of retrofit, refurbishment and estate regeneration (0 to 2m value band) to existing housing across the UK including houses, apartments as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. The Retrofit works may include but are not limited to (i) Internal modernisation, extensive redecoration, (ii) Re-wiring, (iii) Replacing space heating systems, (iv) Replacing doors and windows, (v) Relacing Kitchens and Bathrooms (vi) Essential repairs to the building fabric (vii) Improvements to the energy efficiency of the building (viii) The extension or conversion of an existing building. The estate Regeneration works primarily target the broader physical environment and may include but not limited to (i) Introduction of Landscaping (ii) Repairs to infrastructure (iii) Play areas and equipment. | Construction, Building maintenance and repairs | £100,000,000 |
| Retrofit & Estate Regeneration - Over 2m value band 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of retrofit, refurbishment and estate regeneration (Over 2m value band) to existing housing across the UK including houses, apartments as well as specialist accommodation such as supported living, care facilities, student housing and key worker accommodation. The Retrofit works may include but are not limited to (i) Internal modernisation, extensive redecoration, (ii) Re-wiring, (iii) Replacing space heating systems, (iv) Replacing doors and windows, (v) Relacing Kitchens and Bathrooms (vi) Essential repairs to the building fabric (vii) Improvements to the energy efficiency of the building (viii) The extension or conversion of an existing building. The estate Regeneration works primarily target the broader physical environment and may include but not limited to (i) Introduction of Landscaping (ii) Repairs to infrastructure (iii) Play areas and equipment. | Construction, Building maintenance and repairs | £100,000,000 |
| Demolition Services - 0 to 1m value band 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of full and partial demolition (0 to 1m value band) works across a range of residential and associated non-residential assets, including site clearance and preparation for redevelopment. Works may include soft strip, structural demolition, removal of below-ground obstructions, hazardous material remediation, service disconnections and diversions, and associated enabling works. Appointed companies will be required to deliver a complete end-to-end service, including demolition planning, temporary works, environmental management and site handover, ensuring all activities are carried out in compliance with relevant legislation, health and safety requirements and recognised industry standards. | Construction | £100,000,000 |
| Demolition Services - Over 1m value band 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of full and partial demolition works (Over 1m value band) across a range of residential and associated non-residential assets, including site clearance and preparation for redevelopment. Works may include soft strip, structural demolition, removal of below-ground obstructions, hazardous material remediation, service disconnections and diversions, and associated enabling works. Appointed companies will be required to deliver a complete end-to-end service, including demolition planning, temporary works, environmental management and site handover, ensuring all activities are carried out in compliance with relevant legislation, health and safety requirements and recognised industry standards. | Construction | £100,000,000 |
| Remediation and Enabling Works - Remediation 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of site remediation works required to prepare land for development, including the treatment and management of contaminated land, ground improvement, and associated site preparation activities. Works may include the development and implementation of remediation strategies, removal or containment of contaminants, gas protection measures, verification and validation reporting, and the safe management of materials. Enabling works may include site clearance, earthworks, utility disconnections, ecological and arboricultural protection measures, and the establishment of site access and security. Appointed companies will be responsible for delivering a fully managed service, including the preparation of remediation method statements, compliance with statutory and environmental requirements, and provision of verification documentation to support regulatory approval and site handover. | Construction, Environmental services | £100,000,000 |
| Remediation and Enabling Works - Enabling Works 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of enabling works required to prepare land for development, including the treatment and management of contaminated land, ground improvement, and associated site preparation activities. Works may include the development and implementation of remediation strategies, removal or containment of contaminants, gas protection measures, verification and validation reporting, and the safe management of materials. Enabling works may include site clearance, earthworks, utility disconnections, ecological and arboricultural protection measures, and the establishment of site access and security. Appointed companies will be responsible for delivering a fully managed service, including the preparation of remediation method statements, compliance with statutory and environmental requirements, and provision of verification documentation to support regulatory approval and site handover. | Construction, Environmental services | £100,000,000 |
| Defence Housing & Enabling Works 26 October 2026 to 25 October 2030 What this lot coversThis workstream covers the delivery of new build housing, refurbishment, and associated enabling works within defence and secure environments across the UK, including Ministry of Defence (MoD) accommodation and related infrastructure. Works may include residential development, site preparation, infrastructure and estate regeneration activities, delivered in accordance with project-specific requirements and operational constraints. Appointed companies will be required to deliver a fully managed service, including compliance with enhanced security, information management and personnel vetting requirements, alongside all relevant statutory, technical and government standards. Suppliers must demonstrate the capability to operate within secure environments, including maintaining appropriate certifications (such as cyber security and information management standards), and ensuring continuity of suitably cleared personnel throughout the lifecycle of each project. | Construction, Building maintenance and repairs | £100,000,000 |
Timeline
- Preliminary market engagement notice · UK2, notice 004524-2026
- Tender notice · UK4, notice 039441-2026
About the buyer
Procurements
7Awards
2Suppliers it has used most for construction
- Alpha Building Group Ltd2 contracts
- Blade Roofing Limited2 contracts
- Central Roofing and Building Services Limited2 contracts
- Everlast Waterproofing Limited2 contracts
- Gables UK Ltd2 contracts
Similar open tenders
All open construction tenders- £3mframework ceiling
- £75kestimated
- £400kestimated
- £50mframework ceiling
- £8mframework ceiling
From notice 004524-2026 on Find a Tender, first published 19 January 2026, last updated 29 April 2026. We last checked for changes on 28 September 2026.