AwardedAwarded 5 March 2026
Kings Hall repairs and refurbishment Architect and Design Team
Canterbury City Council · Local authority
In brief
Canterbury City Council awarded architecture and engineering work to DK-CM Limited on 5 March 2026.
The notice gives a value of £160,000 excluding VAT.
The contract runs for 2 years, starting 1 April 2026.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
Canterbury City Council wishes to appoint a suitable supplier for the provision of an Architect /Design Team for Kings Hall Repairs and Refurbishment. The specific requirements for the above are detailed in in the Suite of documents. It should be noted that by submitting a tender, you confirm that you understand and can meet these requirements. It is a condition of the Invitation to Tender for you to attend a mandatory site visit. The site visit will be held on the morning of Tuesday 20 January and Wednesday 21 January 2026. See ITT Instruction Document 2.2.6 for further details. The Contract is anticipated to commence April 2026 and will continue for a period of 2 years (unless terminated…Read the full description
Canterbury City Council wishes to appoint a suitable supplier for the provision of an
Architect /Design Team for Kings Hall Repairs and Refurbishment. The specific
requirements for the above are detailed in in the Suite of documents. It should be noted
that by submitting a tender, you confirm that you understand and can meet these
requirements.
It is a condition of the Invitation to Tender for you to attend a mandatory site visit. The site
visit will be held on the morning of Tuesday 20 January and Wednesday 21 January 2026.
See ITT Instruction Document 2.2.6 for further details.
The Contract is anticipated to commence April 2026 and will continue for a period of 2
years (unless terminated early in accordance with the terms and conditions of the
Contract).
Project Overview :
Canterbury City Council is commissioning a refurbishment and upgrade project at Kings
Hall, Herne Bay. The scope includes:
Fabric Repairs: Essential repairs to the building envelope and internal finishes to preserve
the historic character and ensure long-term durability.
Mechanical & Electrical Services: Upgrading/renewal of existing systems to meet modern
standards for energy efficiency, safety, and operational performance.
Remodeling: To improve functionality and address previous unsympathetic alterations.
This building supports externally accessible public toilets as well as venue facilities. CCC
has developed concept designs which are considered close to meeting our requirements
which include:
Creating an attractive destination seafront bar/cafe separate, yet available to the main
hall.
Improving the main hall and backstage areas, including modernising acoustics and
seating to attract more commercially successful shows.
Exploring opportunities to increase the capacity of the main hall.
The architect will be appointed as Lead Consultant and will be responsible for:
Reviewing and developing CCC's concept designs.
Forming, leading and coordinating a full design team to deliver a complete Turnkey
Service. Identifying all necessary sub-consultants (e.g., structural, civil, M&E engineers,
and any other specialists) Appointing the team directly.
** Advising on and arranging any additional surveys required to bring the project to
completion.
Producing all required outputs in line with the RIBA Plan of Work, from Stage 2 through to
Stage 7.
Delivering a complete design package suitable for procurement via the Kent Business
Portal.
Supporting CCC's appointed Quantity Surveyor throughout the project lifecycle.
Under the CDM Regulations 2015, CCC is the Client and has appointed a Quantity
Surveyor. The architect will be expected to act as Principal Designer. If the architect does
not have the capability to act as Principal Designer, they must propose a suitably qualified
party to fulfil this role and include associated fees in their submission.
*CCC is seeking a complete design package, including any structural, M&E and other
requirements. If the architect does not have the relevant engineering and other expertise
in-house CCC requires them to propose a design team, including these consultants, to
allow them to deliver a complete 'Turnkey Service'. Engineering services and all other subconsultant's fees should therefore be included in this tender submission. All necessary
consultants are to be appointed directly by the Architect.
**The architect should provide details of any additional surveys, including costs, required
to complete the project in their tender submission.
Who won
| Winner | Value | Dates |
|---|---|---|
| DK-CM Limited (SME) | £140,900 | 16 March 2026 to 5 March 2028 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Tender notice · UK4, notice 001800-2026
- Tender notice · UK4, notice 001899-2026
- Contract details notice · UK7, notice 022763-2026
About the buyer
Canterbury City CouncilLast 12 months
Procurements
62Awards
50Suppliers it has used most for architecture and engineering
- Lustre Consulting Limited3 contracts
- HQN Limited2 contracts
- Pillory Barn Design Ltd2 contracts
- Abstruct Consulting Limited1 contract
- Batcheller Monkhouse LTD1 contract
Similar open tenders
All open architecture and engineering tenders- £280mestimated
- £152kestimated
- £5mframework ceiling
- £5mframework ceiling
- £300mestimated
From notice 001800-2026 on Find a Tender, first published 9 January 2026, last updated 13 March 2026. We last checked for changes on 28 September 2026.