AwardedAwarded 13 February 2026
Minor refurbishment of Gamhna Gigha
Northern Lighthouse Board · Central government
In brief
Northern Lighthouse Board awarded construction and building maintenance work to Accted Limited on 13 February 2026.
The notice gives a value of £35,000 excluding VAT.
The contract runs for 2 months, starting 2 February 2026.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
SItuated off the Isle of Gigha, off the West coast of Scotland, this lighthouse can be found in the Sound of Gigha approximately 1⁄2 a mile off the North East corner of Gigha at Latitude 55° 43" 50' N, Longitude -5° 41" 3' W. The lighthouse tower is fixed to the skerries extruding from the sea and the primary means of access to the lighthouse station is by boat from Tayinloan. We require the following works a this lighthouse: 1.Mobilise and take possession of site. 2.Set up site and ensure workplace is secure. 3.Install access steps. 4.Install all safety gate and handrails. 5.Install kick-plate to platform handrails. 6.Prepare and decorate tower and foundation, with appropriate external…Read the full description
SItuated off the Isle of Gigha, off the West coast of Scotland, this lighthouse can be found in the Sound of Gigha approximately 1⁄2 a mile off the North East corner of Gigha at Latitude 55° 43" 50' N, Longitude -5° 41" 3' W. The lighthouse tower is fixed to the skerries extruding from the sea and the primary means of access to the lighthouse station is by boat from Tayinloan. We require the following works a this lighthouse:
1.Mobilise and take possession of site.
2.Set up site and ensure workplace is secure.
3.Install access steps.
4.Install all safety gate and handrails.
5.Install kick-plate to platform handrails.
6.Prepare and decorate tower and foundation, with appropriate external paint specification.
7.Snagging list and handover to NLV staff.
8.Demobilise site.
Appropriate site and specification drawings will be given as part of the full quote documents.
A mandatory site visit is expected to take place on 8th January 2026, we require all interested parties to attend this. Please see the proposed procurement timetable below,
this is intended as a guide and, whilst the NLB does not intend to depart from the timetable, it reserves the right to do so at any time.
Issue of Invitation to Tender -16th December 2025
Site Visit Proposed - 8th January 2026
Clarification deadline - 15th January 2026
Tender return deadline - 4pm 21st January 2026
Tender Award - By 28th January 2026
Commencement of Works - Early February 2026
Completion of Works - By 31st March 2026
Who won
| Winner | Value | Dates |
|---|---|---|
| Accted Limited (SME) 4 bids received | £29,678 | Awarded 13 February 2026 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Tender notice · UK4, notice 083296-2025
- Contract award notice · UK6, notice 035392-2026
About the buyer
Northern Lighthouse BoardLast 12 months
Procurements
51Awards
31Suppliers it has used most for construction
- TRAC HLM Limited6 contracts
- Accted Limited3 contracts
- Dart Industrial Services Limited2 contracts
- Andrew Sinclair Ltd1 contract
- George Brown & Sons Engineers (Leith) Limited1 contract
Similar open tenders
All open construction tenders- £180kestimated
- £4.5mframework ceiling
- Value not stated
- £500kestimated
- £24kestimated
From notice 083296-2025 on Find a Tender, first published 16 December 2025, last updated 17 April 2026. We last checked for changes on 28 September 2026.