AwardedAwarded 26 October 2026
Moveable Shielding Concept Design Study
UK Industrial Fusion Solutions Ltd · Public undertaking
In brief
UK Industrial Fusion Solutions Ltd awarded architecture and engineering and research work to Ove Arup & Partners Ltd on 26 October 2026.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
UKFE has appointed a supplier to provide a Concept Design Study for a Moveable Shielding requirement, as part of the STEP Prototype Power Plant. UKFE is leading the delivery of the STEP programme to design and build the UK’s first prototype fusion energy plant at West Burton, Nottinghamshire.
UKFE ran a below threshold Open competition via FTS and the UKFE Delta portal, which has led to a supplier being appointed.
Who won
| Winner | Value | Dates |
|---|---|---|
| Ove Arup & Partners Ltd | £70,000 | 28 October 2026 to 25 February 2027 |
Values as the award notice gives them, excluding VAT where stated.
Timeline
- Contract details notice · UK7, notice 101853-2026
Last time this was bought
Cryogenic Plant - Design Study - Multi Year
- Awarded
- 26 November 2025
- Value
- £935,285
- Bids
- 3
Matched on UK Industrial Fusion Solutions Ltd, the type of work and the title; it may be a related contract rather than the same one. Check the notice to be sure.
About the buyer
UK Industrial Fusion Solutions LtdLast 12 months
Procurements
99Awards
42Suppliers it has used most for architecture and engineering
- Altrad Babcock Limited4 contracts
- Kyoto Fusioneering Limited4 contracts
- Oxford Sigma Limited3 contracts
- Amentum Clean Energy Limited2 contracts
- NPL Management Limited2 contracts
Similar open tenders
All open architecture and engineering tenders- £312kestimated
- £15kestimated
- £450mframework ceiling
- £280mestimated
- £350mframework ceiling
From notice 101853-2026 on Find a Tender, first published 28 October 2026. We last checked for changes on 28 October 2026.