In brief
Northern Ireland Electricity Networks was looking for suppliers for construction and transport work. Bidding has closed and no award has been published yet.
It is a framework worth up to £37,308,500 excluding VAT: the most the buyer expects to spend across all suppliers, not one contract.
The contract runs for 4 years, up to 8 years with extensions, starting 4 January 2027.
It is split into 6 lots, so a supplier can bid for part of the work.
The buyer says it is suitable for small and medium-sized businesses.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
Lots
| Lot | Trade | Value |
|---|---|---|
| Hire of Large Plant - Area 1 4 January 2027 to 3 January 2031 What this lot coversArea 1 • The provision of track machines / rubber wheel diggers and operators to assist NIE Networks’ teams with: o the erection / replacement of electricity poles, pole mounted apparatus and towers including the installation of stay rods o the installation and repair of substation earthing and associated testing including earth sketches o Vegetation Management using Excavators fitted with suitably designed attachments • Unaccompanied rigging and erection of new poles including collection of materials from NIE Networks’ sites. • Hire of large tracked access equipment inclusive of transportation. • Live pole erection • Loading, transportation and unloading of NIE Networks’ own plant and equipment including but not limited to poles, transformers, conductors, cables and steelwork. • Supplying plant and resources to supplement NIE Networks’ emergency storm repairs • Supplying plant and resources to supplement NIE Networks’ 24-hour fault and emergency response works | Construction, Transport, Vehicles and fleet | £13,810,500 |
| Hire Of Large Plant - Area 2 4 January 2027 to 3 January 2031 What this lot coversArea 2 • The provision of track machines / rubber wheel diggers and operators to assist NIE Networks’ teams with: o the erection / replacement of electricity poles, pole mounted apparatus and towers including the installation of stay rods o the installation and repair of substation earthing and associated testing including earth sketches o Vegetation Management using Excavators fitted with suitably designed attachments • Unaccompanied rigging and erection of new poles including collection of materials from NIE Networks’ sites. • Hire of large tracked access equipment inclusive of transportation. • Live pole erection • Loading, transportation and unloading of NIE Networks’ own plant and equipment including but not limited to poles, transformers, conductors, cables and steelwork. • Supplying plant and resources to supplement NIE Networks’ emergency storm repairs • Supplying plant and resources to supplement NIE Networks’ 24-hour fault and emergency response works | Construction, Transport, Vehicles and fleet | £6,694,000 |
| Lorry Mounted Crane - Contract Lift Area 1 4 January 2027 to 3 January 2031 What this lot coversArea 1 • The provision of a Contract Lift service through Lorry Mounted Cranes to support NIE Networks with the delivery of work within a pre-defined area. • The contractor will perform the Lifting Service under the terms of a ‘Contract Lift’ in accordance with the relevant Regulations and Codes of Practice i.e. Lifting Operations and Lifting Equipment Regulations (NI) 1999 and BS 7121 (Part 4) “Code of practice for: Safe use of Lorry Mounted Cranes”. • Contractors will be required to provide all machinery, vehicles, equipment, PPE and training required to complete the work. • Contractors will be required to supply suitably sized and constructed outrigger support mats to distribute the combined weight of the lifting machine, load and lifting tackle over any one outrigger, depending on varying ground conditions at the location of the lift. • The provision of Lorry Mounted Crane on a Contract Lift basis where the crane company provides a complete package for a given lifting operation. This will include but not limited to the following: o A full lifting plan, method statement and risk assessment o Provision of an appointed person, and where required a Lift Supervisor o Provision of a banksman/slinger o Provision of crane and crane operator o Provision of all tackle and lifting gear o Provision of all insurances | Construction, Transport, Vehicles and fleet | £5,004,000 |
| Lorry Mounted Crane - Contract Lift Area 2 4 January 2027 to 3 January 2031 What this lot coversArea 2 • The provision of a Contract Lift service through Lorry Mounted Cranes to support NIE Networks with the delivery of work within a pre-defined area. • The contractor will perform the Lifting Service under the terms of a ‘Contract Lift’ in accordance with the relevant Regulations and Codes of Practice i.e. Lifting Operations and Lifting Equipment Regulations (NI) 1999 and BS 7121 (Part 4) “Code of practice for: Safe use of Lorry Mounted Cranes”. • Contractors will be required to provide all machinery, vehicles, equipment, PPE and training required to complete the work. • Contractors will be required to supply suitably sized and constructed outrigger support mats to distribute the combined weight of the lifting machine, load and lifting tackle over any one outrigger, depending on varying ground conditions at the location of the lift. • The provision of Lorry Mounted Crane on a Contract Lift basis where the crane company provides a complete package for a given lifting operation. This will include but not limited to the following: o A full lifting plan, method statement and risk assessment o Provision of an appointed person, and where required a Lift Supervisor o Provision of a banksman/slinger o Provision of crane and crane operator o Provision of all tackle and lifting gear o Provision of all insurances | Construction, Transport, Vehicles and fleet | £1,673,000 |
| Mobile Cranes - Contract Lift 4 January 2027 to 3 January 2031 What this lot covers• The provision of a Contract Lift service through mobile and special crane types to support NIE Networks with the delivery of work programmes throughout Northern Ireland. Works will be carried both within live electrical substations up to 400kV and in public/private property locations, within predefined zones, throughout Northern Ireland. • The contractor will perform the Lifting Service under the terms of a ‘Contract Lift’ in accordance with the relevant Regulations and Codes of Practice i.e. Lifting Operations and Lifting Equipment Regulations (NI) 1999 and BS 7121 “Code of practice for: Safe use of cranes”. • Contractors will be required to provide all machinery, vehicles, equipment, PPE and training required to complete the work and will be expected to cover all NIE Networks locations throughout Northern Ireland. • Contractors will be required to supply suitably sized and constructed outrigger support mats to distribute the combined weight of the lifting machine, load and lifting tackle over any one outrigger, depending on varying ground conditions at the location of the lift. • The provision of all crane types must be on a contract lift basis where the crane company provides a complete package for a given lifting operation. This will include but not limited to the following: o A full lifting plan, method statement and risk assessment o Provision of an appointed person, and where required a Lift Supervisor o Provision of a banksman/slinger o Provision of crane and crane operator o Provision of all tackle and lifting gear o Provision of all insurances | Construction, Transport, Vehicles and fleet | £3,850,000 |
| Transportation of Large Plant & Hire of Forklifts / Telescopic Handlers and Associated Lifting Equipment 4 January 2027 to 3 January 2031 What this lot covers• Provision and hire of lorry mounted cranes, forklifts, telehandlers and transport equipment, inclusive of operators to move and install equipment onto site and to recover redundant equipment under Contract Lift terms. • Supplying Portable “A” frame Gantry for the installation of Switchgear. • Supplying plant and resources to supplement NIE Networks’ emergency storm repairs • Supplying plant and resources to supplement NIE Networks’ 24-hour fault and emergency response works | Construction, Transport, Vehicles and fleet | £6,277,000 |
Timeline
- Tender notice · UK4, notice 015539-2026
About the buyer
Procurements
40Awards
21Suppliers it has used most for construction
- Adman Civil Projects Limited1 contract
- Andel Limited1 contract
- Aureos Energy Limited1 contract
- Class One Traffic Management Ltd1 contract
- H&MV Engineering Services Limited1 contract
Similar open tenders
All open construction tenders- £250kestimated
- £15mestimated
- £1mframework ceiling
- £92.8mestimated
- £50mframework ceiling
From notice 015539-2026 on Find a Tender, first published 20 February 2026. We last checked for changes on 28 September 2026.