Highways Works Framework Stage 1 - Conditions of Participation
Metropolitan borough of Bury · Local authority
In brief
Metropolitan borough of Bury was looking for suppliers for construction and highways work. Bidding has closed and no award has been published yet.
It is a framework worth up to £140,000,000 excluding VAT: the most the buyer expects to spend across all suppliers, not one contract.
The contract runs for 4 years, starting 1 July 2026.
It is split into 11 lots, so a supplier can bid for part of the work.
Built from the notice's own fields. Always check the official notice before you bid.
What the notice says
Lots
| Lot | Trade | Value |
|---|---|---|
| Minor and Reactive Maintenance 1 July 2026 to 30 June 2030 What this lot coversDropped crossings (batch delivery), drainage works (routine and urgent), traffic calming, reactive patching and safety works. Typical project values: £10k-£250k. | Construction, Highways and street lighting | £13,426,574 |
| Preventive Maintenance 1 July 2026 to 30 June 2030 What this lot coversSurface dressing (£750k-£1m p.a.), footway slurry sealing (~£200k p.a.), asphalt preservation and in-situ recycling. Typical project values: £50k-£1m. | Construction, Highways and street lighting | £25,174,826 |
| Carriageway Surfacing 1 July 2026 to 30 June 2030 What this lot coversPlaning and resurfacing, full-width surfacing, ironwork adjustments, Patching. Typical project values: £100k-£2.5m. | Construction, Highways and street lighting | £1,678,322 |
| Lining / Anti-skid / Coloured Surfacing 1 July 2026 to 30 June 2030 What this lot coversRoad markings, high-friction surfacing, coloured surfacing and cycle lane treatments. Typical project values: £5k-£50k. | Construction, Highways and street lighting | £13,426,574 |
| Street Lighting 1 July 2026 to 30 June 2030 What this lot coversColumn and lantern replacement, LED upgrades, cabling and feeder pillars. Typical project values: o One-off column replacement (side street incl. TM): ~£1.2k o One-off column replacement (main road incl. TM): ~£2.0k o Small replacement schemes (10 columns): ~£12k-£20k o Large replacement schemes (≈130 columns): ~£260k | Construction, Electrical, Highways and street lighting | £839,161 |
| Major Civils 1 July 2026 to 30 June 2030 What this lot coversJunction improvements, highway realignment, active travel corridors, CRSTS-type schemes. Typical project values: £250k-£10m+. | Construction | £5,034,966 |
| CCTV & Jetting Inspection 1 July 2026 to 30 June 2030 What this lot coversDrainage CCTV surveys, jetting, cleansing and condition assessments. Typical project values: £2k-£25k. | Waste and street cleansing, Environmental services, Architecture and engineering | £419,581 |
| Highway Structures (≤£150k) 1 July 2026 to 30 June 2030 What this lot coversMinor structural repairs, parapet works, bearings and routine maintenance. Typical project values: £10k-£150k. | Construction | £2,400,000 |
| Highway Structures £150k-£750k 1 July 2026 to 30 June 2030 What this lot coversDeck repairs, waterproofing systems, joint replacement and structural repairs. Typical project values: £150k-£750k. | Construction | £9,000,000 |
| Highway Structures over £750k 1 July 2026 to 30 June 2030 What this lot coversTypical project values: £750k-£5m+. Major refurbishments, strengthening works and bridge replacement schemes. | Construction | £18,000,000 |
| Coring 1 July 2026 to 30 June 2030 What this lot coversPavement coring, materials testing and site investigations. Typical project values: £1k-£5k. | Construction | £60,000 |
Timeline
- Planned procurement notice · UK3, notice 083436-2025
- Tender notice · UK4, notice 008664-2026
About the buyer
Procurements
19Awards
4Similar open tenders
All open construction tenders- £40mframework ceiling
- £75kestimated
- £32mframework ceiling
- £160kestimated
- £24kestimated
From notice 083436-2025 on Find a Tender, first published 16 December 2025, last updated 30 January 2026. We last checked for changes on 28 September 2026.